樓頂防水有哪些注意事項
樓頂防水工程怎么做?看了這個實例示范就非常清楚了!本工程為住宅工程,樓頂防水工程為3厚SBS自粘聚合物改性瀝青聚酯胎體防水卷材兩道;40厚C20細石混凝土保護層內配Φ6@150雙向鋼筋。
How to do the roof waterproof project? After reading this example, the demonstration is very clear! The project is a residential project, and the roof waterproof project is two layers of 3-thick SBS self-adhesive polymer modified asphalt polyester matrix waterproof coiled materials; 40 thick C20 fine aggregate concrete protective layer, internal distribution Φ 6@150 Two way reinforcement.
樓頂防水工序與步驟樓頂防水工程的詳細示范簡直是手把手演示樓頂防水樣板策劃根據屋面工程作法確定樣板施工樣式,屋面排水坡度,畫出屋面策劃示意圖。本建筑物總長33.56米,總寬度13.34米,總體南北向排水,坡度2%,東西向排水坡度1%,屋面共設排水口4只,其中北側兩只為側排雨落水口,南側兩只下排雨落水口。
The detailed demonstration of roof waterproof process and steps is simply a hand-in-hand demonstration of roof waterproof model planning. Determine the model construction style and roof drainage slope according to the roof engineering practice, and draw the schematic diagram of roof planning. The building has a total length of 33.56m and a total width of 13.34m. The overall north-south drainage slope is 2% and the East-West drainage slope is 1%. There are 4 drainage outlets on the roof, including two side drainage outlets on the north and two lower drainage outlets on the south.

屋面策劃示意圖屋面排水坡度示意詳圖· 材料進場四方驗收材料進場經過甲方、監理、施工單位及供貨商四方共同檢查并驗收合格。。
Schematic diagram of roof planning, schematic drawing of roof drainage slope · acceptance of materials entering the site. The materials entering the site have been jointly inspected and accepted by Party A, the supervisor, the construction unit and the supplier..